Lagos Coastal Freeway: FG spent N15 billion on waste excavation, design adjustments – Umahi 

The Federal Authorities spent funds to handle waste excavation and street design modifications on the Lagos part of the Lagos–Calabar Coastal Street.

The Minister of Works, Sen. David Umahi, disclosed this on Monday throughout an inspection of the challenge, as reported by the Information Company of Nigeria (NAN).

Umahi defined that the expenditure grew to become essential after engineers found a 50-year-old refuse dump greater than 10 metres deep and spanning two kilometres, forcing a change within the freeway’s alignment to protect present infrastructure.

He additionally highlighted challenges posed by properties alongside the route, together with Landmark Seashore, which required changes to the unique street design.

“Once we began from Kilometre Zero, we encountered Landmark Seashore infrastructure and plenty of different properties alongside the best way. We determined, as a accountable ministry, to differ the design of the challenge,” Umahi mentioned. 

“The implication is that we left the coast and got here to a brand new alignment that was not designed for the challenge,” he added. 

Umahi additional famous the dimensions of the waste problem, stating, “We additionally encountered a refuse dump that had been over 50 years previous, with a depth of over 10 metres and spanning two kilometres. Once we encountered it, we needed to cease the work for greater than 4 months.” 

In accordance with NAN, “He mentioned that tackling the problem value the Federal Authorities N15 billion.” 

Extra insights  

Mr. Dany Abboud, managing director of Hitech Development Firm Ltd., confirmed that main excavation work was carried out between Kilometres 3 and 9, changing waste materials with sand to stabilize the street.

“The most important dump websites have been at Kilometres 4 and 9, which required cautious elimination and substitute,” Abboud famous. 

  • Umahi additionally directed that every one movies, drawings, and challenge documentation be preserved to account for the extra works and prices incurred.
  • Earlier in June, Umahi disclosed that the Federal Authorities had procured contracts value over N3 trillion for sections of the Lagos–Calabar Coastal Freeway spanning Lagos, Akwa Ibom, and Cross River States.

Part I, which begins in Lagos, was procured at N1.068 trillion, with 30% of the contract sum already disbursed. Part II, which incorporates a number of flyovers and crosses swampy terrain linking to the Dangote Refinery, was awarded at N1.6 trillion.

Moreover, Sections III A and III B, overlaying the Akwa Ibom and Cross River segments, have been collectively procured at N1.33 trillion.


..